A drain hole in a hollow SLA print has to work at more than one stage. During printing, an opening can keep a cavity from acting like a suction cup. After printing, the part needs a route for liquid resin and wash solvent to leave. A hole that drains well when you hold the finished part upside down may appear too late in the build to prevent suction.

For a hollow prototype, review when each cavity first opens during the build, where liquid collects after printing, and how the shop will flush and inspect the inside. Check all three before fixing the hole locations in CAD. Formlabs guide to adding holes to SLA models

Start with the cavity, then place the holes

Section the model through each hollow region. Look for ribs that divide the shell, steps that create low pockets and bosses that interrupt a route to the opening. A single shell can contain several separate cavities. Each cavity needs its own access or a connection large enough for the chosen cleaning method.

Then review the model in the proposed build orientation. Scroll through the layers in print order and find the first slice where a pocket behaves like a cup against the tank in a bottom-up SLA system. Check whether an opening already connects it to the surrounding resin at that stage. If the opening prints after several layers of the cup, it cannot relieve suction during those earlier layers. Move the opening or change the orientation, then repeat the slice check. Formlabs guidance on preventing suction cups

The direction that matters can change once the part leaves the printer. In the planned drain position, put an outlet near the low point of the cavity so gravity can empty it. A second opening higher up can admit air and provide a route for flushing. A large accessible opening, such as an existing assembly cutout, may already serve these functions. Check the actual fluid path before adding another hole.

What you see in the modelWhat to check before release
One hollow chamber with a low pocket behind a ribRotate the model into its planned draining position and check whether the pocket empties. Add access or change the internal geometry if liquid would remain.
Two chambers divided by a solid webGive each chamber a usable opening arrangement or add a connection that allows both chambers to drain and flush.
A drain hole beside a support contactCheck that the support tip, raft or removal stub leaves the passage open at the stage when it is needed.
A long narrow channel between two portsConfirm that both ports accept the shop's flushing setup and agree on a check for flow through the finished channel.

Size the opening for cleaning as well as printing

Ask the print provider for the minimum practical drain hole for the printer, resin and orientation. The smallest hole that the machine can reproduce may be awkward to flush or too restrictive for a particular cavity. Wall thickness at the port matters because it sets the length of the passage. A bore through a thick screw boss and an opening through a thin wall can behave differently even when both have the same nominal diameter.

Show the proposed port in section and identify the required clear opening after support removal and finishing. If the shop needs a nozzle to flush the cavity, leave enough access around the opening to position it. Where both an inlet and outlet are available, ask how the shop will confirm that the rinse reaches branches and low pockets. A clear path between two ports may leave a side chamber untouched. Formlabs guide to cleaning internal cavities and channels

Keep drain ports away from sealing lands, snap roots and screw seats unless the opening is part of the design. If a plug is needed for appearance, agree on its fit, finish and seam location. Plan to install it after cleaning, drying and the inspection needed for the cavity. If a port must seal in use, define the test conditions and acceptance criteria for the closure.

Worked example with a handheld enclosure

Consider a display prototype with a continuous visible face, a recessed back and a rib that runs across the hollow interior. The first design puts two holes side by side in the recessed back. In the tilted build orientation, both holes appear late. In the wash position, the rib separates the two holes from a second chamber.

A revised layout puts an opening into the first chamber where it becomes available as the pocket starts to form. It uses a recessed opening at the opposite end for draining and flushing. The second chamber either gets its own access or connects through a cutout in the rib. A rib cutout calls for an assembly check if the rib supports a button or carries a fastener load.

Before approving the layout, review the layers with supports visible. On the first physical sample, check that the ports are open, the cavity can drain in the agreed position and the enclosure still fits its mating parts after finishing. If paint must hide the openings, agree on the closure detail and inspect the visible finish after the plugs are installed.

When a split shell is easier to clean

A split shell exposes internal surfaces for washing and inspection. It can help when a cosmetic exterior allows only small ports, when internal baffles obstruct access or when the team needs to inspect the entire inside surface. The split adds a seam and may need locating features, an assembly fixture or a finish operation. Decide where that seam can sit and how much movement at the joint the prototype can tolerate.

For a small part with a simple shape, ask for solid and hollow quotes if the main reason for hollowing is material savings. Compare the delivered cost and weight along with any extra work for cleaning, plugging and finishing. If the hollow volume is functional, preserve the required cavity dimensions and document how it will be accessed.

What to include in a quote request

  • Send the part CAD and mark any surfaces where holes, seams or support marks are visible to the end user.

  • Identify separate chambers, working fluid channels and any area that must remain accessible for inspection.

  • Specify the intended resin or the prototype requirements, such as stiffness, weight, appearance or fit.

  • Mark critical sealing faces, mounting points and the locations where temporary process holes are allowed.

  • Agree on how to check open ports, dry cavities, channel flow or plug fit where they affect acceptance.

If you are quoting a hollow SLA prototype, include the proposed drain and vent locations with the CAD so the build orientation and cleaning route can be reviewed together. Request a quote from Aluprototype

Frequently asked questions

Does every hollow SLA print need two holes?

The number depends on the geometry and the process. A wide opening can provide enough access for both air and liquid. For a mostly enclosed shell, separate openings often make it easier to vent, drain and flush the cavity. Review each chamber in both the build and draining orientations.

Can a hole drilled after printing prevent suction?

Drilling after printing can provide access for later operations. To relieve suction during the build, the path needs to be open by the time the relevant cavity forms. Include that opening in the print file or adjust the orientation.

Can I leave a hollow cavity sealed for a display model?

If the model needs a seamless appearance, plan how the cavity will be cleaned and dried before closing it. Hidden ports with fitted plugs or a shell assembled after cleaning give the shop access before closure.